Albright  &  Wilson  Ltd  are   a   multinational  chemical  company   manufacturing   phosphates, surfactants,   phosphorous   derivatives  and  acrylics.   At  its  Avonmouth   works  near   Bristol, flame-retardant  chemicals  are manufactured for the treatment of textiles, plastics    polyurethane foams and timber.

SubTerra Engineering was appointed to design and supervise the installation of a  new pipeline for the transfer of treated effluent water to the Wessex Water sewer system located some 500m from the works, as the existing cast iron pipeline had reached the end of its working life.

Project Constraints
The site is located adjacent to  the  A403,  a major route for  HGVs accessing  the M5 motorway, consequently  both the  Client  and Bristol City Council were interested in a scheme that ensured minimal impact on neighbouring sites and traffic flow  during construction.  250m of  the alignment would be adjacent  to  the  public highway, involving crossing the A403,  several  industrial  estate access roads,  a railway  siding,  a  number  of large  diameter culverts, as well as avoiding major services including; gas, water, telecoms, and electricity.  150m  of the  alignment would be within the confines of the plant. Disruption was to  be  kept  to an absolute minimum,  with  the  existing pipeline remaining operational  throughout.  Access  routes  for  emergency  vehicles  were  to be maintained at all times.

Site Investigation
The maximum depth  of  the  proposed pipeline was  anticipated to be 3.0m below ground level. A basic ground investigation  comprising  a  number  of  trial  pits was  considered,  however due  to concerns regarding disruption to the works and the cost of disposing  of  potentially contaminated spoil, a window sampler and dynamic probe rig was utilised.

The window sampler is a compact rig providing a rapid means of acquiring  disturbed  samples  in soft ground. To avoid excavation  within  the works a 100mm  diameter  core was  cut through the reinforced concrete road slab for each sample location The rig was then positioned  over  the hole for testing. The sampler  comprises a  50mm  diameter  hollow tube with a slot  or  window in one side.  This produces a continuous profile of the ground conditions   for soils and chemical testing. The same rig is adapted to carry out dynamic probing to produce a continuous strength profile over the same interval.

The ground was found to consist of a layer of made  ground  (150mm of reinforced concrete within the plant), overlying a soft to firm silty clay, of recent alluvial origin, with occasional peat layers at depth,  with  the   water  table  0.5m  below   ground  level.  Chemical  testing  found  phosphate contamination in  one location within  the plant  although  below threshold  levels.   Information on ground  conditions  and  contamination  was  provided   to  contractors  as  part  of   the  tender documentation, and project Health and Safety Plan.


Design and Route Selection
With all of  the  constraints  in  mind,   SubTerra  Engineering  proposed  the  use  of  trenchless techniques  throughout  the  contract.  Immediate  benefits of using trenchless  techniques  were the rapid issue of  a  street  works  license  from Bristol City  Council  as  no  excavation  on  the  highway would be necessary, and negating the need to  trench  through  the  reinforced  concrete roadways within the plant, thus  minimising  the volume of  potentially  contaminated material  for licensed disposal.

Following  corrosion  trials  with  various  pipe  materials  10bar  MDPE  pipe  was specified,  with electrofusion connections. Two excavations would be required within the plant, one for the pipeline terminal adjacent to the existing pumping station, and one for a rodding point where the alignment required a 90o,  1.5m  radius bend.   Three  rodding  point  manholes  were  required  in  the verge adjacent to the A403 at approximately 100m intervals.

The existing connection to  the  public  sewer  is  via  a 2.5m  deep,  restricted  access  manhole adjacent to a small traffic island.   As the,  however it  was  not possible to utilise this connection and it was considered found to be inadequate. Two new manholes were designed, one acting as a pressure breaking manhole for the  pumped effluent,  with a 3.0m  long gravity pipe  connection to the a second manhole located on  the 2.3m deep public sewer.  This  manhole was subsequently adopted by Wessex Water.

The alignment selected  was  restricted to a  1.0m wide  corridor to avoid two previously installed directional drilled sewers in addition to services.

Construction
Thrustbore Contractors Ltd were awarded the lump  sum  contract  with  a  value of £47,000.  The work was carried out in  spring 1999,  over a period of four weeks.  After excavation of launch pits and  manholes directional  drilling and pipe installation proceeded rapidly,  with  the  alluvial clays proving an  almost ideal medium for this method.   The  drill head was  tracked using  a hand-held detector on surface  which  continuously  receives  information  from  a  transmitter sonde located immediately behind the drill head.  This allows  the plan position and depth to be recorded as well as giving a forward prediction of the drills intended  orientation prior  to the next 3.0m length being drilled. This information enabled the drill to be steered to avoid  obstacles and ensure correct pipe alignment.

Some  difficulties  were  experienced  when  passing below  reinforced concrete,  and the  railway sidings because the steel interfered with the signal from the sonde. However, these errors  tended to average out over short distances, and in all cases the  drill  head emerged at the end  of the run within  a  few  centimetres  of  its  target  position.   After completing each  run  the drill head was removed  and  the  end of the pipe  connected to the drill string to be pulled back through the hole, the ground being sufficiently soft to not require reaming to  a  larger  diameter.  Joints  were made using electrofusion couplers and upon completion the pipeline was pressure tested in accordance with WRC regulations.

The new pipeline was connected to  the pumping station in the plant over a three hour period, after which  the  old  line  was  sealed off  and  abandoned.  The  Contract was completed ahead of the programmed time and on budget.

Back to Projects

A PDF version of this case study is available on the download page


[Home] [Mining] [Tunnels] [No-Dig] [Slopes] [SI] [Site Map] [Contact Us]